Electricity Employees Federation of India

 

    Home | Voice of Electricity workers | Press Release | Resolutions | Feedback | About Us

VOICE OF ELECTRICITY WORKERS

June 2004 -September 2004 Index

 

POWER GRID CORPORATION STRENGTHENING GRIDS
 

Northern region finds a special place in the operations of the corporation. This region proudly boasts of introducing a couple of new technologies to the country. Rihand-Dadri 815 Kms long HVDC link-the first HVDC bipolar project in the country for bulk evacuation of power from Rihand –Singrauli complex to meet the load requirements of Northern Region has been under operation since 1991. The first inter regional 500 MW HVDC back to back link was also established in Northern region at Vindhyachal in 1989 for mutual exchange of power with Western region, further a static VAR compensator of 140 MAVR capacity is working at Kanpur to improve the voltage profile and to enhance security of grid since 1990. Keeping up these traditions, a flexible AC transmission systems (FACTS) – first of its kind; has been constructed at Ballabhgarh at a cost of Rs. 13 crores. This technology has played a very crucial role in voltage regulation, increasing power transfer capability of existing Ballabhgarh Kanpur-transmission line thus huge savings in Capital investment, apart from equitable, power sharing between parallel circuits and enhancing grid reliability. Northern region grid has unique features of having large thermal based generating stations in Eastern portion of the region with major load centres on the Western side. Thus the East West transmission corridor , constituting of a number of 400KV lines of Powergrid supported by the UPPCL; does play vital role in power evacuation and dispersal across. Outage of any line in this corridor upsets the regional balance and has been often a reason of grid disturbances in the past. To overcome these operational constraints in East-West transmission corridor, Power grid has executed a major project by interposing the series compensation on 400 KV Panki-Muradnagar line owned by UPPCL. The project costing about 12 crores is located in 400 KV substation of UPPCL and has been completed in February increasing power transferring capacity of Panki-Muradnagar line by about 150 MW. Otherwise new lines would have been necessary to achieve the same objective which would have been 500% costlier option. Operation of the scheme has been stabilized enabling more power absorption by UPPCL. Further the second phase of Ballabhgarh FACTS project which is the outcome of Powergrid’s R&D efforts in association with BHEL, CPRI, CEA and MIT/GOI is under advanced stages of execution whereby the Thryster Controlled Series feature will be added to the existing project to further enhance its performance level. This phase of the project is expected to be completed very soon. An eminent feature of this scheme has been its indigenous development.


 

Copyright © 2002 - 2004 Electricity Employees Federation of India. All Rights Reserved.
Email: 
info@eefi.org · Feedback · Terms and Conditions ·